PHM Bekapai Pipeline Integrity Assessment
OPERATOR
Pertamina Hulu Mahakam (PHM)
LOCATION
East Kalimantan
CONTRACTOR
AEM SOW
Fitness for Purpose Assessment
PHM intends to develop Bekapai Phase 3, additional wells will be drilled from BH and BE platforms, connecting to BA and BG via existing (partly corroded) 6-inch pipelines.
The following work was undertaken;
- Prepare riser and pipeline stress analysis.
- Pipeline buckling analysis using FEA
- Pipeline freespan analysis
- Pipeline freespan re-analysis BE to BA to Level 3 (CTR-04)
FACILITIES
‐ 6‐inch Pipeline BE to BA
‐ 6‐inch Pipeline BH to BG.