BP Tangguh Expansion Project Images courtesy of Borizontal

OPERATOR

BP Berau

EPCI

LOCATION

Bintuni Bay, Papua

EPCI CONTRACTOR

Lucas Engineering & Construction

AEM SOW

Detail Design Engineering for HDD :
The BP Tangguh Expansion Project (TEP) increases the current 2 LNG trains by additional train of 3.8 TCF via new offshore platforms and new 24-inch pipeline to the existing ORF. HDD engineering support SOW included;
- Work barge stinger design and associated fabrication details.
- Sheet pile anchor design and associated fabrication details, and Pull Back Assembly design.
- Drill pipe stability and recovery.
- Pipe stress analysis and other miscellaneous structural component design.

FACILITIES

‐ 24‐inch Offshore Pipeline to shore